Construction Timeline: MoonSkate

Considering that I already have a functional prototype, I estimate that I will need only about 7 hours of work to create my first MoonSkate design. However, using the rule of 7, this means that I need an additional 49 hours of work in order to reach a desirable design.

Allocation of time (49 hours):

  • Gathering and preparing materials (5 hours)
    • elastic bands
    • obtaining foot straps
    • spray paint
    • peel and stick paper
    • underglow lights
      • LED lighting kit
  • Fabrication and testing (30 hours)
    • Cutting and threading elastic bands through foot straps
    • Tying elastic bands around assembly
    • Stress testing with weight
    • Applying paper and spray paint to exterior
    • Pasting LED lights and testing
  • Additional testing and touch ups (14 hours)
Previous Post
24 Anthropomorphic and Geometric Aesthetics
Next Post
Construction Timeline: Rotary Candle Holder

1 Comment. Leave new

  • Dean Alibrandi
    April 6, 2017 9:37 pm

    Cyron, I think it was really smart how you laid out the work for your project into hours instead of days. A lot of times in scheduling its hard to see how long the actual work will take and that is a great way to budget your time and then put it into a day to day calendar. Seems like you have a good handle on your project so far. Good luck!!

    Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.