Construction Timeline

For my final project, I am creating a tornado desk fountain.

April 4th: Order water pump, jar/vessel, and tubing.

April 4-8: Figure out wiring and base material

April 8 (2 day shipping at best): Plum up vessel and drill hole

April 9-18: Test and adjust hole size and flow rate.

April 18-21: Prepare my final slideshow presentation

April 22: Present the final project to my pod

Previous Post
Construction timeline
Next Post
Construction Timeline

4 Comments. Leave new

I have one of those fountains in my office. Do you want to see it in action?

Reply
Brittany Callin
April 8, 2019 11:13 am

This seems well organized and that you have a plan. I just wonder if you have accounted time for any problems you come across in the project?

Reply
Luke Collier
April 8, 2019 8:27 am

Hi Chris, Good idea to really enumerate the days of the schedule. This will keep you on track.
I wonder how your project is shaping out to be? Have you figured out the wiring, materials, and vessel?
I have some clear-ish PVC tube laying around, some of which I used for a different project. http://www.flowvis.org/2018/03/14/luke-collier-team-2nd/
How hard will it be to create the vortex?

Luke

Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.

Menu