Construction Timeline: wall clock

Week 1 (3/24-3/30)

  • Finish Solidworks models and drawings. Visit machine shop for feedback.

Week 2 (3/31-4/6)

  • Purchase all materials from Homedepot or Amazon.
  • Start manufacturing process.

Week 3 (4/7-4/13)

  • Finish up manufacturing process
  • Product assembly and surface finish

Week 4 (4/14-4/20)

  • Whole week reserved for unknown factors that will delay the original plan.

 

Previous Post
Construction Timeline
Next Post
Construction Timeline

2 Comments. Leave new

[…] Construction Timeline: wall clock […]

Reply
Luke Collier
April 8, 2019 8:44 am

Shen,
I’m so glad you have reserved management time next week! That is a really good idea that I will consider implementing as well. I would love to see what you have made so far.

Reply

Leave a Reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.

Menu