Design Fabrication Timeline

The following is a layout of the schedule for my final project (Wind Chimes).

 

Week of:

March 28: Order supplies from McMaster Carr and pick up supplies form McGuckins.  Also model the pieces in Solidworks.

 

April 4: Begin work in the machine shop, starting with the aluminum pipes.

 

April 11: Finish work in the machine shop

 

April 18: Build model jet and string the whole piece together.

Expo on April 23.

Previous Post
Wind Chime Page
Next Post
Swing Bike: Final Report Page

1 Comment. Leave new

Leave a Reply to Kevin Martin Cancel reply

Your email address will not be published. Required fields are marked *

Fill out this field
Fill out this field
Please enter a valid email address.