Construction Timeline: Dehydrator

Week 1 (Mar 25 – Mar 31):

  • Final Design with dimensions finalized
  • Materials were picked up from home depot

Week 2 (Apr 1 – Apr 5):

  • Material will be cut down to size according to dimensions
  • Fitting test to make sure everything will mate correctly

Week 3 (Apr 8 – Apr 12):

  • Main aesthetic of project will be laser etched into material
  • Dehydrator will be painted black with the etching being highlighted with a much glossier color (Probably silver)

Week 4 (Apr 15 – Apr 19):

  • All internals will be installed and tested.
  • Test subject zero (Strawberries) will be used as a benchmark to show if the dehydrator was successful or not.

1 Comment. Leave new

You must be logged in to post a comment.
Previous Post
Construction Timeline: Iron Punk
Next Post
Construction Timeline